Skip to content
Paradise Valley Reserve Roofing markParadise Valley

Contemporary · Foam recoat · 6-year cycle

Lincoln Drive Foam Recoat — Six-Year Cycle

A foam recoat on a contemporary custom along the Lincoln Drive Corridor — six years from the prior recoat, exactly on the maintenance schedule.

Condition assessment.

The elastomeric coating was at the expected end of its service life — surface chalking on the south and west exposures and two localized micro-blisters at substrate transitions. The underlying foam was intact.

Recommendation.

A targeted repair of the two blistering sites, followed by a full elastomeric recoat to manufacturer specification. No reinstallation required; the system had another full cycle of life with proper maintenance.

Outcome.

A recoat completed within the maintenance window, with documented before/after photography and a written report scheduling the next recoat at the appropriate cadence.